Project overview
- 10,000 PSIG design pressure
- 3 piggable flowline boarding stations
- 2 new flowline heaters
- Riser base gas lift
- Structural deck extensions & access platforms
- Production manifold skids
- Additional HPU & chemical injection
- Piping modifications necessary to tie in the new facilities
- Designed to USCG & BSEE regulations
Scope of work
- Topsides engineering & design
- Regulatory interface & compliance (DNV & BSEE)
- Automation & integration of topsides equipment
- Procurement of all topsides equipment
- Hull & subsea well interface
- Topsides weight control
- Process safety analysis
- Construction management
Project summary
Audubon simultaneously executed the Blue Wing Olive and Red Zinger subsea tiebacks to LLOG’s Delta House, resulting in greater engineering and construction efficiencies. Our scope of work included multidisciplinary engineering and design for the platform’s topsides modifications, procurement, and construction planning and management. The topsides drafting and design team utilized PDMS software for all design work.