PROJECT EXPERIENCE

Bayou Carlin Shallow Water Facility

  1. Home
  2.  | 
  3. Project
  4.  | Bayou Carlin Shallow Water Facility

Bayou Carlin Facility

Bayou Carlin Shallow Water Facility | Audubon Companies | Offshore Deepwater EPC Oil & Gas

Client:

McMoran Oil & Gas LLC

Location:

St. May Parish, LA

Project Summary:

Audubon provided project management, construction management, I&E inspection, and paint inspection for the Bayou Carlin facility. Our team out-fitted a 195-foot by 35-foot barge with equipment to produce 50 million cubic feet per day (MMCFD) of oil. Audubon also oversaw the installation of an 8-inch, 18,000-foot pipeline with two underground bores—one at 4,800 feet and another at 3,000 feet. Additional services for the shallow water facility included cost tracking, procurement support, and vendor surveillance.

Project Overview:

  • 50 MMCFD gas facility
  • 195 ft. X 35 ft. barge
  • Three 1,500 BBLS tanks for oil & water storage
  • 18,000 ft. of 8 in. S80 pipeline
  • Two underground bores: 4,800 ft. and 3,000 ft.

Scope of Work:

  • Project management
  • Construction management
  • I&E inspection
  • Paint tracking
  • Cost tracking
  • Procurement
  • Vendor surveillance