Project overview

  • Inlet separation and inlet coalescer
  • Oil stabilization 2 units
  • Oil storage tanks 3 x 30,000 barrels
  • Oil LACT and pipeline metering and pipeline pumps
  • Condensate stabilization x 1 unit
  • Overhead compression oil and condensate 6 units
  • NGL bullet storage tanks x 2
  • NGL LACT unit and pipeline pumps
  • Pipeline pig launchers and receivers
  • Process water tanks 2
  • Salt water tanks 2
  • Plant flare facilities
  • Utilities: instrument air, start air and fuel gas
  • MCC
  • Sales gas metering
  • Automation/electrical/instrumentation

Scope of work

Project summary

Audubon was appointed as EPCM and fabrication contractor for XTO Energy’s Owl CDP project, a gas processing facility located in Coyanosa, TX. The facility was designed and built-in two phases. The first phase allowed for the processing of 50,000 bpd of oil and included two 25,000 bdp oil stabilization units, inlet surge vessels, three OVHD compressors, two 25MMBTU/hr hot oil systems, two 30,000 bpd floating roof tanks, booster pumps, pipeline pumps, and oil ACT units. Plant utilities included flare, drain, instrument air, control system, power generation, and associated infrastructure. Phase two of Owl CDP included the expansion of the facility to handle 150,000 bpd of oil.

Audubon also provided construction management and commissioning services to the XTO Energy project team as well as developed PSM compliant operating procedures for the facility. Modular processing units were fabricated, shop-tested, and shipped to the site for installation by Audubon affiliate, Opero Energy.

Related services we offer

Detailed Engineering + Design | Services | Audubon
Maximize project value with leading technologies and an agile, dedicated team.
Construction Management | Services | Audubon
Improve productivity and efficiency while reducing downtime and costs.
Asset Integrity+ Corrosion | Services | Audubon
Safely and reliably extend productive life with customized solutions that detect damage and combat corrosion.

Related news + insights

Audubon Wins Turnkey EPC Contract for 275 MM-scfd Cryogenic Plant
Energizing NGL Delivery for WhiteWater Midstream | News | Audubon
Audubon Energizes NGL Delivery for WhiteWater Midstream with EPC Solution
Applying the FEED Phase to Reengineer the Future of Oil + Gas
Esteban Ramos
Esteban Ramos
Country Manager, Audubon