Integrated Engineering-Procurement-Surveying for 2-Bcf/d LNG Supply System
Services
- Detailed engineering + design
- Document control
- Procurement
- Pipeline as-built survey
- Digital data management
Project summary
Developing its first turbine-driven compression station for LNG export presented complex challenges for a North American energy operator—from poor soil conditions and unique coastal regulations to a limited timeline without an active vendor network. Audubon Companies brought an integrated project solution across interconnected assets to deliver a premier, high-capacity LNG supply system.
CHALLENGE: Build critical new infrastructure for LNG export under environmental and supply chain constraints.
To connect significant Haynesville, Marcellus, and Utica shale resources to a global LNG export terminal, an energy infrastructure operator set out to build its first turbine-driven compression station in southern Louisiana to handle 2 Bcf/d of natural gas. The scope extended beyond a single facility, requiring two custody-transfer metering stations and a pipeline interconnect to Port Arthur, Texas.
Environment proved a key challenge for the project—the compression site’s history as a flooded rice field and the delivery metering station’s location near the hurricane-prone coast required specialized civil design and regional expertise. The 72-mi, 42-in pipeline would traverse state and utility crossings, along with sensitive marshes, swamps, and shallow lay lakes. Furthermore, an inherited legacy vendor list and many long-lead items made the procurement phase a risk to schedule and execution.
SOLUTION: Integrate engineering, design, procurement, and surveying across compression, metering, and pipeline assets.
Engineering + design: High-performance compression + metering infrastructure
With engineering proficiency and turbine-compression expertise, the Audubon team designed the operator’s new 2-Bcf/d facility using three Solar® Titan™ 130 units for reliable, efficient performance. We also incorporated all balance-of-plant equipment: skids, vessels, tanks, filter separators, coolers, backup generators, sampling systems, and control systems. For the system’s two metering stations, our engineers and designers focused on accuracy, redundancy, and compliance to support reliable custody-transfer measurement.
Audubon addressed the sites’ Gulf Coast environment with specialized foundation design to ensure infrastructure safety and stability on top of challenging soil. For the near-coast delivery metering station, we designed the facility on an elevated platform to protect critical equipment from storm surge and flooding. Our regional expertise also contributed to seamless navigation of regulatory requirements across multiple federal, state, and local agencies, while meeting the operator’s objectives for emissions reduction.
Procurement: Disciplined, coordinated document control, purchasing, + expediting
Audubon stepped in for the North American energy company with end-to-end procurement services to resolve a gap in resources an protect the project’s schedule. We leveraged established contracts and relationships to source, evaluate, and produce 37 bid packages across 24 suppliers—for a total procurement value of $50+ million, with Audubon assuming full commercial responsibility.
On the front end, our in-house procurement team collaborated with engineering and document control groups to ensure accurate documentation and prevent delays. The group paid special attention to expediting long-lead items, coordinating logistics, negotiating with stakeholders, and prioritizing critical packages. We also rolled out a new Oracle Aconex® system for consistent workflows going forward.
Surveying: As-built confidence + integrated life-cycle data management
For the new LNG supply system on the Gulf Coast, Audubon surveyed the 72-mi, 42-in pipeline connector between the compression station in Beauregard Parish and the export terminal in Port Arthur. We performed an as-built survey across diverse, environmentally sensitive landscapes, while navigating state, utility, highway, bayou, canal,
and river crossings. Highly accurate spatial datasets were captured utilizing advanced imaging technologies, ensuring alignment and constructability from installation through tie-in.
To achieve traceable, verifiable, and complete (TVC) records according to Pipeline and Hazardous Materials Safety Administration (PHMSA) regulations, material tagging and tracking was optimized with our proprietary data management platforms, Audubon Mapping and Project Management (AMPM) and Audubon Integrated Management System (AIMS). Together, the systems created a complete source of truth that the owner will use over the life of the asset for compliant engineering and construction data.
RESULTS: Deliver an on-time, essential supply system for LNG export with 2-Bcf/d capacity, environmental
stability, and TVC data for long-term performance.
Applying an integrated project delivery model for engineering, design, procurement, surveying, and data management—along with regional and disciplinary expertise—Audubon delivered a new, 2-Bcf/d gas transmission system along the US Gulf Coast. With efficient power, resilient infrastructure, and traceable data, this LNG supply system will not only create lasting returns from domestic natural gas; it will serve as a major avenue for energy security and economic growth for decades to come.