PROJECT EXPERIENCE

Patriot Pipeline

  1. Home
  2.  | 
  3. Project
  4.  | Patriot Pipeline

Patriot Pipeline

XTO Patriot Pipeline | Audubon Companies | Project Management of Oil and Gas Pipelines

Client:

XTO Energy

Location:

West Texas

Project Summary:

The Patriot Pipeline project consisted of a 48 mile, 16” pipeline and associated facilities with an aggressive in-service timeline of approximately 12 months from project kick-off. The origination point is near Coyanosa, TX, with delivery near Wink, TX at the Exxon Wink Terminal. As part of the design phase, Audubon Companies was responsible for survey & routing, ROW negotiation/acquisition, permitting and regulatory compliance, engineering, and environmental surveys. As a function of the construction and in-service process, we assisted in the construction management, provided environmental inspection, procurement support, and formulated an integrity management plan. From concept through construction, the EPCM project was successfully delivered within the required timeframe for XTO’s required in-service.

Project Overview:

  • Pipeline Launcher & Receiver
  • Mainline Valve Sites
  • Metering Facility
  • Pressure Let Down & Sample Skid
  • 48 Mile 16 Inch Pipeline

Scope of Work:

  • Pipeline Engineering
  • Project Management
  • Environmental Permitting
  • Survey & Mapping
  • Right of Way
  • Asset Integrity Management
  • Pipeline Integrity
  • Procurement
  • Regulatory Compliance
  • Corrosion Protection